Every commercial window installation is decided before fabrication, not on site. By the time a crew lifts the first frame into an opening, the outcome has already been fixed by four things: a shop drawing frozen against a measured opening, a survey that recorded what the building actually built, an anchor and flashing sequence the frame was detailed to receive, and a handover file the inspector will ask for by name. Get those right and installation becomes execution — predictable, inspectable, repeatable across a hundred openings. Get them wrong and no amount of site skill recovers the façade, because a frame cannot be widened on site, a drained joint cannot be reordered after the fact, and a certificate cannot be retrofitted to a configuration it never covered. This guide is written from the factory side of that boundary: what a manufacturer must lock before the drawing is released, and what the installing crew needs in hand to finish the job.

The distinction matters most in export work, where factory, distributor and installing contractor are three companies in three time zones. At project scale, a commercial windows installation is a chain of handovers, and each one is a place where a measurement, a responsibility or a document can fall through. This guide maps them for contractors, project managers and distributors buying from a Chinese factory — including where supply stops and a local commercial window installation service begins.

Who Does What: Supply-Only, Supply-and-Install, and Site Supervision

A project can buy the aluminum units, the installation, or both under one contract, and the three models carry different risks for whoever signs the façade package. Units are fabricated to approved drawings in Foshan and shipped FOB from Nansha, Shekou or Yantian. Installation is labour that must stand in the opening, so it belongs to a crew on site — the buyer's own commercial window installers or a local contractor under a single contract.

Supply-only. The factory fabricates, pre-assembles, crates and delivers; the buyer's team surveys, sets, flashes, glazes, seals and warrants the result. This is the default export model, and it fails in one predictable way: the buyer assumes the factory has measured something it has never seen. In supply-only the survey is the buyer's responsibility.

Supply-and-install. One party answers for product and installation — overseas, almost always a local partner employing the crews, because installation cannot be shipped in a container. Where a project contracts this way with us, the factory supplies drawings, pre-assembly verification, a method statement and, only where the contract agrees it, technical attendance at named hold points; the installing entity remains responsible for workmanship and the wall interface.

Site supervision and technical attendance. A middle path: the buyer's crew installs, with technical attendance from the factory — survey review and setting of the first unit — only where the contract agrees it. It removes most interpretation risk on an unfamiliar system.

Whichever model applies, the boundary must be written rather than assumed. Water at the perimeter is where blame lands first, and the joint between frame and wall belongs to whoever built the opening and closed the seal. Name in the contract who supplies the sealant, who owns the mock-up, who signs each hold point, and who issues which warranty.

When a project appoints one of the commercial window installation companies that will hold that interface warranty, ask five questions: for a method statement written against your system rather than glazing in general; which substrates the crew has anchored into; whether they will attend a factory pre-assembly review; for their hold-point checklist and who signs it; and what their own warranty covers. A cheaper bid usually removes survey labour and hold-point attendance, not material.

ActivitySupply-onlySupply-and-installSupply with technical attendance
Site survey and remeasureBuyer's installerInstallerBuyer's installer, factory reviews the record
Shop drawings and fabricationFactoryFactoryFactory
Delivery and hoistingBuyerInstallerBuyer
Setting, shims and anchorsBuyer's installerInstallerInstaller; technical attendance at the first unit where the contract agrees it
Flashing and wall interfaceBuyer's installerInstallerInstaller
Glazing and perimeter sealantBuyer's installerInstallerInstaller
Final adjustment and cycle testBuyer's installerInstallerInstaller; factory technical review where the contract agrees it
Product warrantyFactoryFactoryFactory
Installation and watertightness warrantyBuyerInstallerBuyer's installer
Handover fileFactory documents, buyer compilesInstaller compilesFactory documents plus installer records

Before Fabrication: The Drawing Freeze

The drawing freeze is the moment the fabrication set is signed and placed under revision control. After it, every change costs money and schedule, because profiles are cut, glass is ordered and finish batches are loaded against that set. It is the most consequential date in the order.

A complete package carries the opening schedule keyed to elevation and room number; the setting-out drawing with anchor, packer and weep positions; the glass build per elevation, with laminate where safety glazing requires it; the hardware schedule and the handing of every operable; the finish per elevation with colour reference and colour count; the head, jamb and sill details including flashing; and the movement allowance at the head. Where a detail is missing, the factory assumes one, and the assumption stays invisible until the unit is on site.

Revision control is part of the freeze: one drawing number per elevation zone, one revision letter, and a transmittal log recording who received which revision. A change phoned to a project manager and never drawn is the origin of most arguments at handover.

The freeze also fixes the batch. Minimum order quantities are set per series and per finish, so each series and finish carries its own MOQ, even when several series share one container; the logic is set out in our guide to aluminum window MOQ in China. Lead time runs 25–45 days after deposit and drawing freeze for standard finishes and glass builds, which makes the freeze the start clock — a late survey pushes the freeze and the fabrication start, and consumes the float the project counted on.

Five-step commercial window installation sequence from site survey to sealant and handover
The sequence the freeze commits the project to: survey and remeasure, shim and anchor, flashing, glazing, then sealant and handover.

Site Survey and Opening Tolerance

The survey is the only measurement that matters. Architectural drawings describe intent; the survey records what exists, and the frame is manufactured once, to one set of dimensions. Fabricating from the architectural set is the most expensive shortcut in the chain, because every deviation is absorbed later by a shim, a cover trim or a sealant joint that was never designed to take it.

A usable survey records, per opening: clear width and height at head, sill and mid-height; both diagonals, because a parallelogram passes a width check; reveal depth; sill level and fall; jamb plumb; substrate condition at each anchor; the finished floor allowance; and any obstruction inside the opening zone. Photographs numbered to match the sheet make the survey evidence rather than opinion.

Tolerance is where survey and drawing must agree before anything is cut. Acceptable deviation is declared by the project specification and confirmed on the approved shop drawings; the survey measures the opening against that allowance, not against a number the site team remembers. When an opening falls outside it, the answer is a design decision with three legitimate forms: build up the opening, add a subframe or extension profile, or re-detail the interface. The illegitimate answer is a deeper sealant joint, which fails at the first serious thermal cycle.

The signature on the survey sheet belongs to the party that owns the opening, and the date belongs to the week before the freeze. A project that cannot survey in time delays fabrication or accepts the risk explicitly — it does not fabricate from drawings and hope.

The commercial window installation sequence, step by step

The order of work is a dependency chain: each step creates the surface the next one seals against. A crew that understands why the order is fixed will protect it under schedule pressure, which is exactly when it gets broken.

StepKey actionsHold pointIf it is skipped
1. Verify and prepareRemeasure against the approved survey; check diagonals, sill level and substrate; set the first bay as a mock-upSigned survey and first-unit sign-offErrors surface after anchoring, when the frame is already cut
2. Set, shim and anchorPlace packers, plumb and level, check diagonals, torque anchors to the approved detailDiagonal and plumb check before torqueTwist closes the drainage path and misaligns every operable
3. Flash and integrateSill pan lapped over the weather barrier, ends turned up; barrier over the flashing at head and jambsLap inspection before any sealantWater bypasses the frame and enters the wall cavity
4. GlazeClean pocket, setting blocks, glass, gaskets, beads per the drawingEdge clearance and bead retentionGlass bears on metal; cracked panes and whistling joints
5. Seal and hand overTwo-stage joints, verify every weep is open, adjust operables, compile the fileWeep and joint inspection, cycle testA sealed weep turns the sill into a reservoir

Anchors go in before flashing because the flashing must cover the fastener penetrations; glazing follows flashing because perimeter work around an open pocket disturbs blocks and gaskets; sealant comes last because it must bond to clean, lapped, cured surfaces. Reverse the order and a drained assembly becomes an adhesive one, with a single line of defence.

A storefront run follows the same logic at a different rhythm: commercial storefront window installation sets the continuous sill first, plumbs the verticals off it and sets the head to the verticals, so mullion alignment sets the elevation and glass is placed last rather than first. Drainage stays continuous through the run, and the interior floor finish usually goes in afterwards — exactly when an outlet gets buried by a tiler who does not know it exists.

Unitised curtain wall changes the sequence again: complete panels are set one by one from a floor, so slab-edge accuracy replaces individual opening measurement as the dominant risk. The commercial aluminum window frames guide covers the frame decisions behind these systems.

Anchors, Shims and Structural Transfer

A frame is a load path, not a decorative surround. Wind load pushes and pulls horizontally, the dead load of glass acts vertically, and building movement arrives from the slab. Every force leaves the frame through the anchors, which is why the anchor detail is a structural drawing rather than a site choice.

Anchor selection follows the substrate. Concrete, structural steel, masonry and light-gauge framing each demand a different fixing, and within concrete the choice between mechanical, chemical and cast-in provision depends on edge distance and embedment. The approved drawings set type, spacing and embedment; where the specification requires it, pull-out verification confirms the substrate behaves like the one assumed in design. Recording which anchor went into which opening is the only way to answer a question about one bay two years later.

Packing does two jobs and belongs to two different details. Glazing setting blocks under the glass carry dead load, placed per the glazing detail at the specified hardness. Frame packers beside each anchor let tightening clamp the frame instead of pulling it toward the structure, and are set per the anchor detail. Neither may bridge the thermal break or block a weep. Over-torque one corner and the diagonals change — the sash stops sitting square, gasket contact goes uneven and the glass is stressed in a way the detail never anticipated. Check diagonals before final torque and again afterwards.

The head detail normally allows for slab deflection: the head slip joint lets slab deflection pass the frame instead of loading the glass. A frame rigidly fixed at head and sill will pass its water test on commissioning day and leak in the first season of occupancy.

Flashing, Sealant and the Drainage Path

A commercial window is drained, not sealed. The design assumes some water passes the outer gasket under wind-driven rain and provides a path for it to leave: a cavity, a weep, a sill slope, an outlet. Sealant terminates that system at its edges; a joint detailed as if it replaced the system will be the first thing to fail.

Flashing follows shingle logic, but the lap direction differs by edge: at head and jambs the wall weather barrier laps over the flashing; at the sill the pan flashing laps over the weather barrier and turns up at the ends, so the pan — not the barrier — is the top layer where water drains outward. Nothing relies on an uphill lap. At the sill the turned-up ends act as end dams, because water running along a sill will find the corner and run into the wall.

Sealant joints are two-stage. A backer rod sets the depth that lets the sealant stretch and compress and stops it bonding to the back of the joint. Width and depth come from the manufacturer's published joint design rather than a rule of thumb, and the substrate must be clean, dry and primed where required. Temperature and moisture at application decide whether the joint cures or skins over, so sealant is scheduled work with weather conditions attached.

Weeps are what good intentions destroy: a painter sealing a slot, a cleaner blocking a baffle, a bead run across the base of a storefront. Each converts a drained sill into a reservoir. Check every weep at handover and mark it on the maintenance drawing.

Glazing and Final Adjustment

Glazing is a separate trade step, and commercial glass window installation is its own discipline even when the same crew sets the frames. Some units arrive factory-glazed, which shifts the risk to packing and handling; others ship with glass separate because the unit is large, the access is restricted, or the glass comes from another supplier. The method is a line in the drawing set.

Site glazing has non-negotiables. The pocket is clean and dry before the glass goes in. Setting blocks sit where the detail puts them, in the specified hardness, because a hard block in the wrong place concentrates load on a pane edge. Edge clearance keeps glass off metal at every perimeter. Gaskets are seated without being stretched or pinched, corners mitred and sealed where the system calls for it, and beads retained as drawn — a bead removable from outside on a ground floor is a security question before a weather one. Labels stay on until handover.

Units travel and store on edge, never flat and never twisted; a chipped edge or damaged edge seal is a rejected unit, not a touch-up. A-frames off the ground and away from traffic do more for the programme than supervision at the opening.

After glazing, work each operable through a full cycle: sash square, lock compression even along the full height, weatherstrip in contact without being crushed, sash weeps clear. Adjust hinges and rollers to the hardware instructions, then re-check the seal line, because the seal is what the water test measures. Doors follow a different commissioning logic, covered in the commercial aluminum doors guide.

Handover Documents a Commercial Project Will Ask For

The handover file is assembled during the job. Every document below has a moment when it is cheap to produce and a moment when it is impossible, and the gap is usually a week on site. Assign an owner to each line at the pre-construction meeting.

DocumentIssued byWhen it is required
Approved shop drawings with revision logFactoryBefore fabrication release
Opening survey record with photographsBuyer's installerBefore the drawing freeze
Certification scoped to the certified series and configuration; other material certificates per contractFactoryAt submittal
Factory QC and pre-assembly recordsFactoryBefore shipment release
Packing list keyed to zone and floorFactoryWith the shipping documents
Method statement and hold-point checklistFactory and installerBefore mobilisation
Anchor and substrate verificationInstallerAt the anchor hold point
Marked-up as-built drawingsInstallerAt practical completion
Cleaning and maintenance instructionsFactoryAt handover
Warranty documents, product and installationFactory and installerAt handover

Two rows are the ones most often faked. Certification is scoped: a certificate names the series and configuration it was issued against, and one naming a different series does not cover the elevation it is filed under. Warranty is split: product warranty as stated in the quotation and contract; installation and watertightness warranty sits with the installing party. A file holding only one leaves the owner without an answer when water appears.

Where Installation Goes Wrong in Export Projects

Cross-border projects fail in predictable patterns. A survey arrives after production release, so frames are cut to drawings the site has already contradicted. An RFI is raised at the end of the crew's day and answered at the end of the factory's. Consumables run short — gaskets, screws, cover caps, the specified sealant — small enough for a suitcase, large enough to stop a floor. A subcontractor changes a detail and never draws it. Crates are opened by a crew that does not read the zone labels. The building is not watertight when the units arrive. When a joint leaks, the first instinct is more sealant, the one remedy that cannot work on a drained system.

Most are mitigated before the container is loaded: survey before production release, with the record signed; a spares allowance packed with the shipment for the gaskets and caps most likely to be damaged; crates labelled by zone and floor; one named technical contact on each side, with a response window across the time difference; photo-based hold points at survey, first unit, flashing and sealant.

Documents and money travel on the same timetable. Deposits, balance and document release are agreed at order — commonly T/T 30/70 on a first order; a large or first order may run on an L/C at sight — and the aluminum window payment terms guide sets out how those milestones line up with inspection and booking. FOB Nansha, Shekou or Yantian decides which forwarder books the space, not whether the document set is complete before the container leaves.

A commercial window package is a documentation project with a manufacturing step inside it. Send the elevation, the opening schedule and the destination port through our contact page, and the reply is a drawing-based proposal rather than a catalogue price.

Frequently Asked Questions

Can we buy the windows without the installation?

Yes. Supply-only is the standard export model: we fabricate to approved drawings, pre-assemble, crate and deliver FOB Nansha, Shekou or Yantian, and your installer takes over at the port or on site. In that model the buyer owns the survey, setting, flashing, sealant and watertightness warranty, while product warranty on the units is as stated in the quotation and contract. It works well for contractors with an established crew and badly for projects that assume the factory has measured an opening it has never seen.

The opening is larger than the frame. Can we just seal the gap?

No. A sealant joint sized to close a construction error exceeds the movement capacity of the sealant and fails at the first thermal cycle, usually at the head or sill where water is already present. The legitimate options are to build up the opening, add a subframe or extension profile, or re-detail the interface. Which applies depends on the direction and size of the deviation, so the decision belongs with the party that owns the opening and should be documented before anything is fixed.

Can the sequence be reversed to suit the programme?

Not the weather-critical part. Anchors precede flashing because the flashing must cover the fasteners; glazing follows flashing because perimeter work around an open pocket disturbs blocks and gaskets; sealant comes last because it must bond to clean, cured surfaces. You can run several floors in parallel and glaze a completed bay while another is still being anchored, but within one opening the order is fixed.

How do we inspect the order before it ships?

Pre-assembly and photographic or video witness at the factory against the approved drawings, with the scope written into the contract before the order is placed. The inspection covers frame assembly, hardware operation, drainage paths and finish, and it is a common trigger for the balance tranche, which is normally due against the B/L copy — confirm the milestone in the contract. Because units ship FOB, the buyer's forwarder takes over at the port, so the packing list keyed to zone and floor matters as much as the inspection itself.

How long does fabrication take once the order is placed?

Production runs 25–45 days after deposit and drawing freeze for standard finishes and glass builds, counted from the signed freeze rather than the purchase order. The freeze is the real start date, which is why an incomplete survey does not delay the factory; it eats the buffer the project was relying on. Minimum order quantities are set per series and per finish, so consolidating series and colours at the freeze is usually what protects the schedule.